Project References |
 |
|
|
|
10MWp Grid-connected Power Station in Qingtongxia,Ningxia | |
|
|
 |
Location: |
New Material Foundationin Qingtongxia,Ningxia |
 |
Scale: |
10MWp |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
China Datang Renewable Power Co.,Ltd |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
Started in Feb 15,2011 and combined to the grid in Sep 28,2011 |
|
|
| |
|
|
40MWp Grid-connected Power Station in Lingwu,Ningxia | |
|
|
 |
Location: |
Baitugang Town, Lingwu City,Ningxia |
 |
Scale: |
40MWp |
 |
Details: |
Polycrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Three Gorges New Energy Angli (Lingwu) Power Generation Co.,Ltd |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
Started in Sep 28,2012 |
|
|
| |
|
|
39MWp Grid-connected Power Station in Lingwu,Ningxia | |
|
|
 |
Location: |
Baitugang Town, Lingwu City,Ningxia |
 |
Scale: |
39MWp |
 |
Details: |
Crystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Datang Angli (Lingwu) Renewable Power Co.,Ltd |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
Started in Sep 28, 2011 and combined to the grid in Dec 28,2011 |
|
|
| |
|
|
10KWp Substation PV DC System in Ningdong,Ningxia | |
|
|
 |
Location: |
Ningdong City,Ningxia |
 |
Scale: |
10kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Ningxia Ningdong Administration of Power Supply |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
15 working days |
|
|
| |
|
|
10KWp Substation PV DC System in Zaozhuang,Shandong | |
|
|
 |
Location: |
New Hi-tech Zone Zaozhuang City,Shandong |
 |
Scale: |
10kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Zaozhuang Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
25 working days |
|
|
| |
|
|
5KWp Substation PV DC System in Zaozhuang,Shandong | |
|
|
 |
Location: |
Tengzhou, Zaozhuang City,Shandong |
 |
Scale: |
5kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Zaozhuang Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
15 working days |
|
|
| |
|
|
5KWp Substation PV DC System in Zaozhuang,Shandong | |
|
|
 |
Location: |
Zaozhuang City,Shandong |
 |
Scale: |
5kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Zaozhuang Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
20 working days |
|
|
| |
|
|
5KWp Substation PV DC System in Heze,Shandong | |
|
|
 |
Location: |
Heze City,Shandong |
 |
Scale: |
5kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Heze Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
15 working days |
|
|
| |
|
|
5KWp Substation PV DC System in Laiwu,Shandong | |
|
|
 |
Location: |
Laiwu City,Shandong |
 |
Scale: |
5kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Laiwu Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
15 working days |
|
|
| |
|
|
5KWp Substation PV DC System in Linyi,Shandong | |
|
|
 |
Location: |
Linyi City,Shandong |
 |
Scale: |
5kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Linyi Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
15 working days |
|
|
| |
|
|
5KWp Substation PV DC System in Weihai,Shandong | |
|
|
 |
Location: |
Weihai City,Shandong |
 |
Scale: |
5kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Weihai Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co., Ltd |
 |
Construction Period: |
15 working days |
|
|
| |
|
|
5KWp Substation PV DC System in Zouping,Shandong | |
|
|
 |
Location: |
Zouping County,Shandong |
 |
Scale: |
5kW |
 |
Details: |
Monocrystalline solar panels installed with steel bracket in fixed angle |
 |
Investor: |
Shandong Electric Power Group Company Zouping Power Supply Company |
 |
Contractor: |
Atsun Solar Electric Technology Co.,Ltd |
 |
Construction Period: |
15 working days |
|
|
| |